Madison Street Bridge Reopened
After a summer of detours to get into Rockwell, the Madison Street Bridge is reopened for traffic.
The bridge officially opened at 1:00 p.m. on Friday, July 25, just 50 working days after Taylor Construction started renovating the bridge earlier this summer.
"They did a tremendous job," said Public Works Director Jay Siefken, who noted that Taylor Construction completed the job 20 days ahead of schedule. "The bridge could have been open a week earlier if the sign company had shown up to paint the lines."
Read the full article in the Aug. 7 edition of the Enterprise.